Project Phases & Milestones

TMSP Project Milestones

B Pedestrian Tunnel ReopensQ3-2026
Outer Roadway Substantial CompletionQ2/Q3-2027
Concourse A Demolition Substantial CompletionQ2-2026
Administration Building Steel Erection BeginsQ2-2026
Administration Building Structure CompleteQ3-2026
Administration Building Substantial CompletionQ2/Q3-2027

Phasing Overview

Our objective is to develop the best phasing strategy that aligns design and construction with:

• Safety
• Passenger flows and wayfinding
• Baggage handling/processing
• Airline operations
• Tenant impacts

The Design and Construction Team developed and evaluated numerous phasing plans over the last several months. 

The current plan, while a work-in-progress, provides the basic elements of each major phase.

5 Major Phases

7 Areas

 

Overall Phasing Plan

Plaza/Basement Level

Baggage Claim / Arrivals Level

Ticketing Lobby / Departures Level

Mezzanine Level

Roof Level

Enabling Phase

Baggage Claim / Arrivals Level

Gold-colored areas indicate construction zones.

Ticketing Lobby / Departures Level

Phase 1A

Baggage Claim / Arrivals Level

Ticketing Lobby / Departures Level

Phase 1B

Baggage Claim / Arrivals Level

Ticketing Lobby / Departures Level

Phase 2A

Baggage Claim / Arrivals Level

Ticketing Lobby / Departures Level

Phase 2B

Baggage Claim / Arrivals Level

Ticketing Lobby / Departures Level

Phase 2B

Baggage Claim / Arrivals Level

Ticketing Lobby / Departures Level

Phase 3A

Baggage Claim / Arrivals Level

Ticketing Lobby / Departures Level

Phase 3B

Baggage Claim / Arrivals Level

Ticketing Lobby / Departures Level

End State

Plaza / Lower Level

Baggage Claim / Arrivals Level

Ticketing Lobby / Departures Level

Mezzanine Level